Bringing AI capacity online
What determines when planned AI infrastructure becomes operational?
Edited by Finquill Research · Updated Oct 27, 2026
Review cadence: Weekly review; re-checked on named earnings and filing dates. Not daily.
Reviewed by the editor · Analytics, not advice
Free account. See what changed since your last visit, and the dates to watch on your calendar. Following never means agreeing.
Short answer (filings to 20 Oct 2026). At the operators that publish milestones, capacity is coming online faster than a year earlier. The documented holdups are specific rather than general: one provider's late delivery of data centers, and suppliers' own capacity. Grid evidence differs by region. None of the operator filings read here attributes a delay to power at sites already under way. But regulators and grid operators in Ireland, Great Britain, Texas and the PJM region are rationing or re-sorting the queue of new requests, which is where a power limit would show first. A request, a forecast or an allocation is not a connection.
What changed in this update
The first update, published Oct 27, 2026.
What's next
Dated tests · set down in advance, graded by the editor
Nov 30, 2026 · CRWV
CoreWeave's Form 10-Q for the quarter ended 30 September 2026 still expects the single-site lease's undelivered power in phases in 2026 and 2028, and the other leased sites' undelivered power between 2026 and 2028.
Mar 31, 2027 · CRWV
CoreWeave reports active power at 31 December 2026 above the 1.5 GW it reported at 30 June 2026.
Mar 31, 2027 · NBIS
Nebius reports at least 5 GW of contracted power at the end of 2026.
Open questions
- CoreWeave Q3 2026 (results date not yet announced; 10-Q due by 16 Nov): how much active power did it add in the quarter, after nearly 500 MW in Q2, and are the delivery windows for 393 MW and 355 MW of undelivered power unchanged?
- CoreWeave FY2026 10-K (about early March 2027): what was active power at 31 December 2026, against 1.5 GW at 30 June?
- Nebius Q3 2026 (date not announced; last year 11 Nov): does it report active or connected megawatts, not only contracted power, and is the 5 GW year-end target unchanged?
- Ofgem's decision on demand-connection reform (pending) and ERCOT's first batch study: how much of each queue is removed, and how much is reserved?
- Does any operator disclose a dated baseline and a changed delivery date for a named site in its own filing?
- OCCTO's next demand forecast (January 2027) and Ireland's CSO 2026 edition (mid-2027): does the slippage in data-centre demand persist, and does Ireland's share keep rising?
Already happened
These dates have passed; the questions are kept as they were asked.
- Oct 23, 2026 · EIA Electric Power Monthly (monthly; the 23 Oct release, with data through August, is not yet reflected here): do Virginia's and Texas's commercial electricity sales keep growing faster than the US total?
The analysis
Operator milestones
- CoreWeave's active power was about 70 MW at end-2023, about 360 MW at end-2024, about 590 MW at 30 September 2025, over 850 MW at end-2025, over 1 GW in Q1 2026 and 1.5 GW at 30 June 2026. Contracted power was about 3.7 GW at 30 June and about 4.2 GW by 11 August.
- Its June 10-Q gives dated windows: 393 MW still undelivered at a single-site lease, expected in phases in 2026 and 2028, and 355 MW at other leased sites between 2026 and 2028. The March 10-Q described the same leases as providing access to 525 MW and 363 MW. The wording changed, so the difference is not a clean count of megawatts delivered.
- Oracle says its quarter to 31 August included delivery of 850 MW of additional datacenter capacity. Nebius, based in Amsterdam, expects 5 GW of contracted power by end-2026 and plans to deploy more than 1 GW a year from 2027.
The one documented delay
- Baseline (12 August 2025): about 470 MW active and about 2.2 GW contracted; 2025 guidance of $5.15–5.35bn revenue and $20–23bn capex.
- Change (November 2025): on 10 November CoreWeave cut 2025 guidance to $5.05–5.15bn revenue and $12–14bn capex. Its 10-Q of 13 November cited "recently announced delays" in the delivery of certain data centers by a third-party data center provider.
- Outcome: active power still rose, from about 590 MW at 30 September to over 850 MW at end-2025. The 10-K cites the delays announced in November 2025 as an example of third parties failing to deliver. The provider and the site are not named, and the filings do not quantify the delay.
Equipment and components
- ASML expects its currently planned supply for 2027 and 2028 will not fully meet customer demand (October 2026). In July it planned to add 30% to its 2026 low-NA EUV capacity of around 65 systems for 2027.
- SK hynix began mass shipments of HBM4 in Q2 2026 and is accelerating its M15X fab schedule; its Yongin Phase 1 cleanroom opens in early 2027.
- NVIDIA says the availability of land, power, shell and capital is crucial to its customers' buildouts, that expanding them is a complex, multi-year process, and that customers may postpone purchases when data-centre infrastructure is not available.
Grid access, region by region
- PJM (US Mid-Atlantic and Midwest): near-term years count large loads only with firm commitments. The January 2026 forecast puts the summer-2027 peak at 160,451 MW, 2.3% below the prior forecast, while summer-peak growth over ten years averages 3.6% a year.
- ERCOT (Texas): large-load requests rose from about 410 GW in March to about 474 GW in June 2026, about 90% of them data centres. ERCOT says restudies can extend timelines by years, and it is moving to batch studies.
- Ireland: data centres used 23% of metered electricity in 2025, up from 5% in 2015. Since December 2025, new data centres of 10 MVA or more may not operate or ramp up until associated onsite or nearby generation is delivered.
- Great Britain: contracted demand in the connection queue grew from 41 GW to 125 GW between November 2024 and June 2025, about 73 GW of it data centres, against a 2025 peak demand of 45 GW. Only 32% of data-centre projects responding to the system operator had secured an off-taker.
- Japan: the national grid coordinator's January 2026 forecast pushes data-centre demand later than its previous forecast, citing operators' construction postponements, delays and design changes. Data-centre demand stays below the earlier forecast through FY2033.
- Elsewhere: nearly 5 GW of Finnish data-centre projects had signed connection agreements by mid-August 2026. Singapore provisionally allocated 200 MW to four operators, about 12% of its data-centre capacity. The European Commission puts EU capacity at about 12 GW in 2025, rising to around 28 GW by 2030.
- Metered use, where it exists: commercial-sector electricity sales from January to July 2026 rose 6.6% in Virginia and 7.0% in Texas, against 3.5% nationally (EIA, preliminary; not data-centre-specific).
What this does not show. No source measures how much of the delivered capacity is in use. No issuer filing here gives both a dated baseline and a changed delivery date for a named project. Request queues (474 GW in Texas, 125 GW in Great Britain) are far larger than what is being built, so they measure interest, not demand that will connect. Regional findings stay in their region.
Strongest alternative
Power and equipment, not buildings, may become the binding limits, just not yet in operators' disclosures. Regulators already act as if power were. Ireland makes new data centres bring their own generation, Great Britain is redesigning its demand queue, ERCOT is batching studies, and Japan's grid coordinator says data-centre plans are slipping. Upstream, ASML expects its currently planned supply for 2027 and 2028 will not fully meet customer demand. On this reading, today's operator milestones come from sites that secured power and equipment years ago, and the next wave will arrive later than contracted-power figures imply.
A second alternative points the other way: queues and forecasts overstate what will be built. Many requests are speculative or duplicated. PJM now derates non-firm projects, and only 32% of British data-centre projects had an off-taker. So "shortage" headlines may mistake the rationing of speculative requests for a constraint on real projects.
Developments
Oct 14, 2026
ASML: planned 2027–28 supply will not fully meet demand
ASML said its currently planned supply for 2027 and 2028 will not fully meet customer demand, as order momentum rose quarter on quarter.
An equipment limit two years out, named by the supplier itself.
1 report · one development
Reports sharing an origin are coverage, not independent confirmation.
Aug 11, 2026
CoreWeave reaches 1.5 GW of active power; 393 MW at one lease still undelivered
CoreWeave added nearly 500 MW in Q2 to reach 1.5 GW of active power and about 3.7 GW of contracted power, and reported 393 MW still undelivered at a single-site lease.
Sets the dated tests for the Q3 10-Q and the FY2026 10-K.
1 report · one development
Reports sharing an origin are coverage, not independent confirmation.
Jul 29, 2026
ERCOT: 474 GW of large-load requests, about 90% data centres
ERCOT told the Texas Senate it is tracking about 474 GW of large loads seeking interconnection, up from about 410 GW in March, with about 205 GW preliminarily eligible for its first batch study.
Request queues are growing far faster than connected load; the batch study is the next test of how much is real.
1 report · one development
Reports sharing an origin are coverage, not independent confirmation.
Jul 29, 2026
Ofgem consults on reforming Great Britain's demand queue
Ofgem said contracted demand in the connection queue rose from 41 GW to 125 GW between November 2024 and June 2025, about 73 GW of it data centres, and proposed reforms to sort it.
A second non-US regulator moving to ration data-centre connections; its decision is pending.
1 report · one development
Reports sharing an origin are coverage, not independent confirmation.
Mar 2, 2026
CoreWeave ends 2025 above 850 MW; its 10-K keeps the delays as a risk example
CoreWeave's 10-K reports over 850 MW of active power at end-2025, up from about 590 MW at 30 September, and cites the delays announced in November 2025 as an example of third parties failing to deliver on their contracts.
The outcome of the documented delay: active power kept rising through the quarter, and the filing names neither the provider nor the site.
1 report · one development
Reports sharing an origin are coverage, not independent confirmation.
Jan 21, 2026
Japan's grid coordinator pushes data-centre demand later
OCCTO's FY2026 demand forecast moves data-centre demand later than its previous forecast, citing operators' construction postponements, delays and design changes; it stays below the earlier path through FY2033.
A non-US, forecast-level signal of slipping data-centre plans, attributed by the grid coordinator itself.
1 report · one development
Reports sharing an origin are coverage, not independent confirmation.
Dec 12, 2025
Ireland requires new data centres to bring their own generation
Ireland's energy regulator decided that new data centres of 10 MVA or more may not operate or ramp up until associated onsite or nearby generation is delivered.
A regulator rationing new data-centre connections, in the country where data centres use the largest share of electricity.
1 report · one development
Reports sharing an origin are coverage, not independent confirmation.
Nov 10, 2025
CoreWeave cuts 2025 guidance; its 10-Q cites a provider's data-center delays
CoreWeave cut its 2025 guidance to $5.05–5.15bn of revenue (from $5.15–5.35bn) and $12–14bn of capex (from $20–23bn). Its 10-Q, filed on 13 November, cited recently announced delays in the delivery of certain data centers by a third-party data center provider.
The one provider-level delivery delay CoreWeave's filings document; the filings do not link it to the guidance change.
2 reports · one development
Reports sharing an origin are coverage, not independent confirmation.
Evidence
Sources: CoreWeave, Inc. (SEC Form 10-K, FY2025) ×2 · CoreWeave, Inc. (SEC Form 10-Q, Q2 2026) ×2 · Oracle Corporation (SEC Form 8-K Ex. 99.1, Q1 FY2027 ended 2026-08-31) ×2 · SK hynix Inc. (newsroom press release, Q2 2026) ×2 · NVIDIA Corporation (SEC Form 10-Q, Q2 FY2027 ended 2026-07-26) ×2 · PJM Interconnection (PJM Inside Lines, 2026 Long-Term Load Forecast summary) ×2 · and 30 more
CoreWeave, Inc. (SEC Form 10-K, FY2025) · Mar 2, 2026
As of December 31, 2023, we operated 10 data centers with approximately 70 MW of active power. As of December 31, 2024, we operated 32 data centers with approximately 360 MW of active power. As of December 31, 2025, we operated 43 data centers with over 850 MW of active power. As of December 31, 2025, our total contracted power capacity was approximately 3.1 GW, which we expect to deploy over future periods.
Scope and limits: Company-defined metrics, not audited. Elsewhere in the same 10-K the 2024 figure is phrased as "more than 360 MW". No timetable for the 3.1 GW in this sentence.
Retrieved Oct 21, 2026.
CoreWeave, Inc. (SEC Form 8-K Ex. 99.1, Q2 2025 results) · Aug 12, 2025
Continued rapid scaling of our purpose-built AI Infrastructure. We ended the quarter with approximately 470 MW of active power and we increased total contracted power approximately 600 MW to 2.2 GW
Scope and limits: Company metrics for the quarter ended 30 June 2025, unaudited and undefined in the release. The release gives no year-end active-power target.
Retrieved Oct 22, 2026.
CoreWeave, Inc. (SEC Form 8-K Ex. 99.1, Q3 2025 results) · Nov 10, 2025
Continued rapid scaling of Purpose-Built AI Infrastructure ◦Added approximately 120 MW of active power in the quarter, bringing the total to approximately 590 MW ◦Expanded total contracted power to approximately 2.9 GW while further diversifying our portfolio of providers
Scope and limits: Company metrics, unaudited, undefined in the release.
Retrieved Oct 21, 2026.
CoreWeave, Inc. (SEC Form 8-K Ex. 99.1, Q1 2026 results) · May 7, 2026
Revenue backlog1 was $99.4 billion as of March 31, 2026. […] Continued Rapid Scaling of Purpose-Built AI Infrastructure ◦Surpassed 1 GW of active power ◦Expanded total contracted power by more than 400 MW to over 3.5 GW while further diversifying portfolio of providers
Scope and limits: Company metrics, unaudited. The release says "Surpassed 1 GW", not a precise figure.
Retrieved Oct 21, 2026.
CoreWeave, Inc. (SEC Form 8-K Ex. 99.1, Q2 2026 results) · Aug 11, 2026
Continued Rapid Scaling of Purpose-Built AI Infrastructure ◦Expanded active power by nearly 500 MWs to reach 1.5 GW ◦Grew total contracted power to approximately 3.7 GW while further diversifying portfolio of providers and expanding powered land footprint
Scope and limits: Company-defined operating metrics ("active power", "contracted power") without a definition in this release; not audited; contracted power is a forward pipeline, not delivered capacity.
Retrieved Oct 21, 2026.
CoreWeave, Inc. (SEC Form 424B5 prospectus supplement, 17 September 2026) · Sep 17, 2026
In addition, between June 30, 2026 and August 11, 2026, we added more than $25 billion of net new customer commitments early in the third quarter of 2026 and increased our total contracted power to approximately 4.2 gigawatts as of August 11, 2026 from approximately 3.7 gigawatts as of June 30, 2026.
Scope and limits: Intra-quarter company metric as of 11 August 2026, unaudited; contracted power is a forward pipeline, not delivered or active capacity. Q3 2026 results were not yet published as of 21 Oct 2026.
Retrieved Oct 22, 2026.
CoreWeave, Inc. (SEC Form 10-Q, Q2 2026) · Aug 11, 2026
The aggregate amount of estimated future undiscounted lease payments associated with such leases is $35.5 billion. These leases will commence between 2026 and 2029 with estimated lease terms of seven to sixteen years. Not included in the preceding amount of estimated future undiscounted lease payments are the following lease arrangements, which include significant uncertainties regarding the amount of future lease payments. As of June 30, 2026, the Company also had a lease agreement for various buildings located at a single site intended to be used as a data center. As of June 30, 2026, 393 MW of electrical power remained undelivered at the site and was expected to be delivered in phases in 2026 and 2028. The Company will make contractual rent payments based on […] construction costs incurred by the lessor, subject to a contractual maximum of $14.7 billion over the sixteen year term of this lease. Additionally, the Company has lease agreements where the lease payments are based on a portion of the construction costs incurred by the lessor. The payments during the construction period are variable and subject to contingencies, which are expected to be resolved at or near the lease commencement date. As of June 30, 2026, 355 MW of electrical power remains undelivered at these sites and are expected to be delivered in phases between 2026 and 2028.
Scope and limits: Covers only leases excluded from the $35.5bn figure because their payments are uncertain; not CoreWeave's total undelivered contracted power. Site and lessor are not named. Wording changed from Q1 2026 (Q1 described total access, Q2 describes undelivered power), so MW are not a like-for-like delivery count.
Retrieved Oct 21, 2026.
CoreWeave, Inc. (SEC Form 10-Q, Q1 2026) · May 7, 2026
The aggregate amount of estimated future undiscounted lease payments associated with such leases is $40.7 billion. These leases will commence between 2026 and 2029 with estimated lease terms of five to sixteen years. Not included in the preceding amounts are the following lease arrangements, which include significant uncertainties regarding the amount of future lease payments. As of March 31, 2026, the Company also entered into a lease agreement for various buildings located at a single site intended to be used as a data center. The agreement provides access to 525 MW of electrical power, which is expected to be delivered in phases in 2026 and 2028. The Company will make contractual rent payments based on construction costs incurred by the lessor, subject to a contractual maximum. The total contractual rent payments range from $18.7 billion to $19.6 billion over the sixteen year term of this lease. Additionally, the Company has lease agreements where the lease payments are based on a portion of the construction costs incurred by the lessor, including during the construction period. The payments during the construction period are variable and subject to contingencies, which are expected to be resolved at or near the lease commencement date. As of March 31, 2026, these lease agreements provide access to 363 MW of electrical power, which is expected to be delivered in phases between 2026 and 2028.
Scope and limits: Q1 wording is total MW access under the leases; Q2 wording is MW remaining undelivered (393 / 355). The difference (525 to 393; 363 to 355) cannot be read as MW delivered without company confirmation. The single-site rent figure also changed from a $18.7-19.6bn range (Q1) to a $14.7bn contractual maximum (Q2), unexplained in the excerpts.
Retrieved Oct 21, 2026.
CoreWeave, Inc. (Q3 and FY 2025 Outlook presentation, Aug 12, 2025) · Aug 12, 2025
Q3 Guidance Revenue $1.26 – 1.30 billion Full Year Guidance Revenue $5.15 – 5.35 billion Adjusted Operating Income $160 – 190 million Interest Expense Adjusted Operating Income $800 – 830 million $350 – 390 million Capital Expenditures Capital Expenditures $2.9 – 3.4 billion $20 – 23 billion
Scope and limits: Read as plain text, the slide's two columns (Q3 guidance; full-year guidance) interleave; the slide's own layout places $5.15–5.35 billion revenue and $20–23 billion capital expenditures in the full-year column. Guidance, not results.
Retrieved Oct 21, 2026.
CoreWeave, Inc. (FY 2025 Outlook presentation, Nov 10, 2025) · Nov 10, 2025
2025 Full Year Guidance Full Year Guidance Revenue $5.05 – 5.15 billion Adjusted Operating Income $690 – 720 million Interest Expense $1.21 – 1.25 billion Capital Expenditures $12 – 14 billion
Scope and limits: Guidance on the company's own "capital expenditures" definition, not the cash-flow line; the FY2025 cash purchase of P&E was $10.3bn.
Retrieved Oct 21, 2026.
CoreWeave, Inc. (SEC Form 10-Q, Q3 2025) · Nov 13, 2025
In addition, while we have entered into various agreements for the lease of data center space, equipment, maintenance, and other services, those third parties could fail to deliver on their contractual obligations under those agreements, including agreements to provide us with certain data, equipment, and utilities information required to run our business, such as the recently announced delays with respect to the delivery of certain data centers to be provided by a third-party data center provider. Any failure by our third-party data center providers to timely deliver on their agreements with us would have an adverse effect on our business, operating results, financial condition, and prospects.
Scope and limits: Risk-factor language in the 10-Q for the quarter ended 30 September 2025, filed three days after the 10 November results. The provider and the sites are not named, no MW, revenue or timing impact is quantified, and the excerpt does not link the delays to the guidance change.
Retrieved Oct 22, 2026.
CoreWeave, Inc. (SEC Form 10-K, FY2025) · Mar 2, 2026
In addition, while we have entered into various agreements for the lease of data center space, equipment, maintenance, and other services, those third parties could fail to deliver on their contractual obligations under those agreements, including agreements to provide us with certain data, equipment, and utilities information required to run our business, such as the delays that we announced in November 2025 with respect to the […] delivery of certain data centers to be provided by a third-party data center provider.
Scope and limits: Risk-factor language; the provider is not named and no MW or revenue impact is quantified here. A page-break marker in the source ("16 Table of Contents") is elided with […].
Retrieved Oct 21, 2026.
Oracle Corporation (SEC Form 8-K Ex. 99.1, Q1 FY2027 ended 2026-08-31) · Sep 10, 2026
Total quarterly revenues increased 30% to $19.3 billion, reflecting strong execution in our infrastructure business, with the delivery of 850MW additional datacenter capacity. […] Oracle generated Q1 GAAP operating income of $6.7 billion, up 57%, while non-GAAP operating income rose to $8.2 billion, up 31%, driven by continued broad-based demand in Cloud Infrastructure and Cloud Applications. […] Oracle’s strong operating income translated to a record Q1 operating cash flow of $23 billion, up 184%. Free cash flow was negative $5 billion for Q1 as Oracle continued to execute on investments to support the growth of its Cloud Infrastructure business.
Scope and limits: Oracle's fiscal Q1 runs June-August, so it does not line up with calendar Q3. Operating cash flow includes $11.4 billion of customer prepayments (shown in the same release's cash-flow statement). The 850MW figure is a company statement with no definition (IT load versus gross).
Retrieved Oct 21, 2026.
Oracle Corporation (SEC Form 8-K Ex. 99.1, Q1 FY2027 ended 2026-08-31) · Sep 10, 2026
•Remaining Performance Obligations or RPO up $209 billion year-over-year to $664 billion […] Customer demand for AI Cloud Training and Inferencing Services continues to grow faster than supply. Oracle booked more than $30 billion of additional AI cloud contracts in Q1 increasing its RPO to $664 billion. Based on the structuring of those new contracts, the Company confirms there is no incremental impact on its plans to raise capital. Since the end of Q4, Oracle also delivered more than 300,000 GPUs to its AI Cloud customers and almost triple the capacity delivered in Q4 FY26.
Scope and limits: RPO is contracted but unrecognised revenue; the release gives neither customer concentration nor the timing of recognition. GPU counts and "almost triple" are company statements without a capacity unit.
Retrieved Oct 21, 2026.
Nebius Group N.V. (SEC Form 6-K Ex. 99.2 shareholder letter, Q2 2026) · Aug 12, 2026
We now anticipate ending 2026 with 5 GW of contracted power(5), up from the +4 GW we indicated last quarter. The pace at which we bring capacity to market will accelerate as we plan to deploy more than 1 GW per year, starting in 2027.
Scope and limits: US dollars; calendar fiscal year; unaudited. Footnote 5 defines contracted power as secured by contracted land and power commitments; it is not active, energized or GPU-loaded power. No active or connected MW figure is given in the letter text. Sites named in the letter: additional Q2 sites in the UK, Estonia and Finland; owned US AI factories under construction.
Retrieved Oct 21, 2026.
Microsoft Corporation (FY2026 Q4 earnings call transcript, company IR site, 2026-07-29) · Jul 29, 2026
Revenue growth was ahead of expectations driven by efficiency gains across our CPU and GPU fleet as well as process improvements to enable earlier delivery of new capacity.
Scope and limits: This is management's explanation; the call gives no figure for how much each factor contributed.
Retrieved Oct 21, 2026.
Microsoft Corporation (SEC Form 10-K, fiscal year ended 2026-06-30) · Jul 29, 2026
Demand for cloud-based and AI products and services is evolving and difficult to forecast. Overestimation of demand or misalignment of capacity investments may result in underutilization of infrastructure and may lead to impairment of assets on our balance sheet. Conversely, demand exceeding available capacity limits our ability to meet customer needs in a timely manner. […] In many regions, electricity generation, transmission, and distribution infrastructure is experiencing increasing demand and capacity constraints. Limitations in power availability, delays in obtaining power connections, outages, shortages, increased energy costs, or requirements imposed by utilities, regulators, or other market participants could restrict our ability to develop or expand datacenter capacity.
Scope and limits: Risk factors describe possibilities, not measured constraints; nothing here quantifies unmet demand or delayed capacity. The measured "demand exceeds capacity" statement comes from the earnings call (separate sources in this narrative).
Retrieved Oct 21, 2026.
ASML Holding N.V. (SEC Form 6-K, Q3 2026) · Oct 14, 2026
With such strong visibility and an order book momentum that continues to increase quarter on quarter this year, we now expect that our supply as currently planned for both 2027 and 2028 will not fully meet the demand of our customers
Scope and limits: Figures in euros under US GAAP; ASML quarters end on a Sunday (Q3 2026 ended September 27, 2026). Forward-looking; no 2027 sales guidance is given. A footnote marker follows "customers" in the source; the footnote refers to the Q2 2026 plan to add 30% to low NA EUV and DUV immersion capacity in 2027. The next sentence says ASML is investigating capacity for 2028 beyond the previously communicated 30% increase.
Retrieved Oct 21, 2026.
ASML Holding N.V. (SEC Form 6-K, Q2 2026) · Jul 15, 2026
Based on this momentum, we are planning to add 30% to our 2026 low NA EUV capacity of around 65 for 2027, and we are investigating to increase capacity with another 30% for 2028.
Scope and limits: Figures in euros under US GAAP; ASML quarters end on a Sunday (Q3 2026 ended September 27, 2026). Capacity plan, not shipments or orders; "around 65" is approximate. Superseded in part by the Q3 2026 statement that 2027-2028 supply as planned will not fully meet demand.
Retrieved Oct 21, 2026.
SK hynix Inc. (newsroom press release, Q2 2026) · Jul 29, 2026
The company began mass shipments of HBM4 in the second quarter and will ramp up production in the second half of the year.
Scope and limits: Korean won, consolidated K-IFRS, calendar fiscal year; preliminary figures subject to change in the independent audit (per the release). Qualitative; no HBM volume, revenue share or customer named.
Retrieved Oct 21, 2026.
SK hynix Inc. (newsroom press release, Q2 2026) · Jul 29, 2026
In response, SK hynix is accelerating the mass production schedule for M15X while making investments to rapidly expand production capacity following the opening of the Yongin Phase 1 cleanroom in early 2027.
Scope and limits: Korean won, consolidated K-IFRS, calendar fiscal year; preliminary figures subject to change in the independent audit (per the release). No capex amount or capacity in wafers is given; the release separately stresses "CapEx Discipline" and phased execution of P&T7, M17 and a new cluster based on customer demand.
Retrieved Oct 21, 2026.
NVIDIA Corporation (SEC Form 10-Q, Q2 FY2027 ended 2026-07-26) · Aug 26, 2026
Customers may postpone purchasing new architectures due to the lack of availability of data center infrastructure to deploy our products, constraints on capital to have sufficient funding to purchase our products, or may adopt new technologies more gradually than anticipated, affecting our revenue timing and supply chain expenses. The availability of land, power, shell, and capital is crucial to support the buildout of a full data center inclusive of NVIDIA AI infrastructure by our customers and partners, and any shortage of these or other necessary resources could impact our future revenue and financial performance. Expanding land, power, shell, and energy needs to meet demand is a complex, multi-year process that involves significant regulatory, technical, and construction challenges. In addition, access to capital can be particularly constrained for less-capitalized companies, which may face difficulties securing financing for large-scale infrastructure projects. We believe AI clouds and AI model makers have significant demand for training and inference compute and currently lack the ability to secure long-term infrastructure contracts and investment-grade financing capacity to secure the AI infrastructure necessary to grow.
Scope and limits: Qualitative management discussion in MD&A, not a risk factor. No quantification of postponed purchases.
Retrieved Oct 21, 2026.
NVIDIA Corporation (SEC Form 10-Q, Q2 FY2027 ended 2026-07-26) · Aug 26, 2026
Commitments, guarantees, and other commercial arrangements expose us to financial, counterparty and execution risks and may not provide anticipated benefits. […] Future demand may be affected by the ability of customers and partners, including those developing open models, to generate revenue and sustain investment in computing infrastructure. […] Customers or partners may fail to fulfill their financial commitments, secure necessary capital or infrastructure, complete projects on schedule or within budget, or experience financial distress or insolvency. Power constraints, government actions or regulations, permitting delays, or community opposition may delay, restrict or prevent the development or operation of data centers. […] Under the agreements, if AI clouds do not successfully sell committed capacity to third-party customers, we have agreed to purchase that capacity.
Scope and limits: Risk-factor language describes possibilities, not events that have occurred; no probabilities or amounts in this passage (amounts are in Notes 8 and 10).
Retrieved Oct 21, 2026.
PJM Interconnection (PJM Inside Lines, 2026 Long-Term Load Forecast summary) · Jan 14, 2026
2027 160,451 -3,735 (-2.3%) 2026/27 142,536 -4,155 (-2.8%) 2028 165,567 -4,414 (-2.6%) 2027/28 147,807 -5,759 (-3.8%) […] 2035 216,872 +6.949 (+3.3%) 2034/35 199,622 +1,477 (+0.1%)
Scope and limits: Planning forecast (January 2026 vintage), not observed load; non-coincident unrestricted peaks; MW changes are vs the prior (2025) forecast, not vs actuals. Page table has at least one typo (+6.949) and one inconsistent percentage (+0.1%).
Retrieved Oct 21, 2026.
PJM Interconnection (PJM Inside Lines, 2026 Long-Term Load Forecast summary) · Jan 14, 2026
Near-term forecast years are considered to be needing “firm” commitments […] while longer-term projects will be considered “non-firm” and will be derated […] This distinction has brought large load adjustments down in the near-term forecast years compared with the 2025 Long-Term Load Forecast.
Scope and limits: Describes forecast methodology, not how much data-center load actually materialises; no MW quantity for the derating in this passage.
Retrieved Oct 21, 2026.
PJM Interconnection (2026 PJM Load Forecast Report, January 2026) · Jan 14, 2026
The 2026 Long-Term Load Forecast is lower than the 2025 Long-Term Load Forecast in the near term through 2032 due to updates to the electric vehicle forecast, economics and large load adjustments.
Scope and limits: Qualitative attribution; no split of how much each cause contributes in this sentence (the Inside Lines post gives summer-2026 drivers: large loads -0.7%, economics -0.5%, EVs -0.1%).
Retrieved Oct 21, 2026.
PJM Interconnection (2026 PJM Load Forecast Report, January 2026) · Jan 14, 2026
Summer peak load growth is projected to average 3.6% per year over the next 10-year period and 2.4% over the next 20 years. • Summer peak is forecasted to be 222,106 MW in 2036, a 10-year increase of 65,733 MW, and reaches 253,077 MW in 2046, a 20-year increase of 96,704 MW.
Scope and limits: Long-term planning forecast, not observed load; values are non-coincident unrestricted peaks after solar/battery reductions and EV additions, before load management.
Retrieved Oct 21, 2026.
ERCOT (Update to Texas Senate Committee on Business & Commerce, April 1, 2026) · Apr 1, 2026
Large Load Interconnection Requests (as of March 26, 2026) Actual and Projected Large Loads Growth 2022-2030 Large Loads by Project Type […] Key Takeaway: ERCOT is tracking approximately 410 GW of Large Loads seeking interconnection of which ~87% are data centers.
Scope and limits: Requests seeking interconnection, not approved, contracted or energized load; requests can be speculative or duplicated. Superseded by ERCOT's July 29, 2026 update (~474 GW, ~90% data centers).
Retrieved Oct 21, 2026.
ERCOT (Update to Texas Senate Committee on Business & Commerce, July 29, 2026) · Jul 29, 2026
Key Takeaway: ERCOT is tracking approximately 474 GW of Large Loads seeking interconnection, of which ~90% are data centers. […] Approximately 205 GW of Large Load is eligible for inclusion in Batch Zero based on existing studies
Scope and limits: Requests and preliminary eligibility, not approved or energized load; ERCOT said final Batch Zero determinations come on or before Aug 7 with results by Sep 2, 2026 (later figures not checked here).
Retrieved Oct 21, 2026.
ERCOT (Update to Texas Senate Committee on Business & Commerce, April 1, 2026) · Apr 1, 2026
projects can be repeatedly pulled into restudies as new requests enter the system, delaying approvals and potentially extending timelines by years […] Every ~6 months, all submitted requests are clustered and studied together; allocated capacity coming out of the study is “reserved”
Scope and limits: Process description on a slide; no measured delay statistics. Batch Zero timeline and rules were still in stakeholder review at the time.
Retrieved Oct 21, 2026.
Lawrence Berkeley National Laboratory (Queued Up: 2026 Edition, data through 2025) · May 1, 2026
The dataset includes requests submitted to queues through the end of 2025, and only includes generation requests seeking to connect to the transmission grid (i.e., does not include load interconnection requests nor distribution-connected or behind-the-meter projects).
Scope and limits: Generation/storage supply-side queue only, so it cannot be used to size data-centre (load) requests. Landing page says Date Published 05/2026 (month only); the PDF deck is dated June 2026.
Retrieved Oct 21, 2026.
U.S. Energy Information Administration (Electric Power Monthly Table 5.4.B, data through July 2026) · Sep 24, 2026
Table 5.4.B. Sales of Electricity to Ultimate Customers by End-Use Sector, by State, Year-to-Date through July 2026 and 2025 (Thousand Megawatthours) […] Virginia 28,526 28,933 51,089 47,929 […] Texas 97,549 97,976 105,463 98,541
Scope and limits: Commercial sector is a proxy that includes many data centres but also all other commercial customers, and utilities classify customers differently (some data centres are billed as industrial). Preliminary cutoff-sample estimates; retail sales only (excludes self-supplied/behind-the-meter).
Retrieved Oct 21, 2026.
U.S. Energy Information Administration (Electric Power Monthly Table 5.4.B, data through July 2026) · Sep 24, 2026
U.S. Total 892,279 894,810 889,286 859,409 […] Values are preliminary estimates based on a cutoff model sample.
Scope and limits: Same caveats as the state rows: commercial sector is not a data-centre series; preliminary estimates subject to revision.
Retrieved Oct 21, 2026.
JLL (press release, North America Data Center Report - Midyear 2026) · Aug 11, 2026
With vacancy sustained at 1% for the third consecutive year despite unprecedented construction activity, North America now has 66 GW under construction, 95% of which is pre-committed.
Scope and limits: Broker market research on its own site; JLL definitions of vacancy, "under construction" and "pre-committed" are not given in the sentence and differ from CBRE's primary-market figures; not audited.
Retrieved Oct 21, 2026.
CoreWeave, Inc. (SEC Form 10-Q, Q2 2026) · Aug 11, 2026
For example, government authorities have in the past sought to restrict data center development based on environmental considerations and have imposed moratoria on data center development, such as the moratorium on the development of data centers using 50 megawatts of power or more in the State of New York that was announced in July 2026.
Scope and limits: Risk-factor language; it does not say whether any CoreWeave site is affected or quantify impact. The underlying New York action should be sourced from the State of New York itself before being stated as fact.
Retrieved Oct 21, 2026.
Central Statistics Office, Ireland (Data Centres Metered Electricity Consumption 2025, Key Findings) · Jul 7, 2026
The percentage share of total metered electricity consumption used by data centres rose to 23% in 2025 from 5% in 2015 (See Table 1). Metered electricity consumption by data centres increased by 10% in a single year, rising from 6,973 Gigawatt hours (GWh) in 2024 to 7,663 GWh in 2025.
Scope and limits: Metered electricity consumption (energy actually delivered through ESB Networks meters), Republic of Ireland only. CSO notes there is no agreed definition of a data centre and identifies them by searching ~2.6 million meters; all years are subject to revision, and new sites below search thresholds may be missed. Excludes any on-site/private-wire generation not passing through those meters. It is not a measure of utilization, and not a count of delayed projects. The Key Findings page prints '07 July 2025' in its header while the landing page and statistician's comment say 07 July 2026; 2026 is correct for a 2025 dataset.
Retrieved Oct 21, 2026.
Commission for Regulation of Utilities, Ireland (Decision paper CRU/2025236, Large Energy Users Connection Policy) · Dec 12, 2025
The Commission has made a decision that new data centres with an MIC equal to or above 10 MVA cannot be operational or ramp up their demand without achieving delivery of associated onsite or proximate generation.
Scope and limits: A connection-policy rule for NEW applications, not a measure of capacity connected, consumption, or utilization; it does not say how many projects will qualify or proceed. It is a precondition on energisation, not an observed project delay. EirGrid's AIRAA 2026-2035 dates this policy's publication to 16 December 2025, but the CRU page says 12 December 2025.
Retrieved Oct 21, 2026.
Commission for Regulation of Utilities, Ireland (Decision paper CRU/2025236, Large Energy Users Connection Policy) · Dec 12, 2025
Initial feedback from this market intelligence exercise suggests that there is potential for in the order of 5.8GW additional demand capacity required for the data centre sector in Ireland in the medium term. This is in addition to demand already contracted
Scope and limits: Prospective developer demand gathered by the electricity and gas system operators for the CRU, described as 'initial feedback'; not contracted, not connected, not consumption, and no year is given for 'medium term'. It is not a measure of utilization, and not a count of delayed projects.
Retrieved Oct 21, 2026.
EirGrid (All-Island Resource Adequacy Assessment 2026-2035, Ireland) · Feb 26, 2026
In Ireland, there is approximately 2,100 MVA of demand capacity that is contracted to data centres and other new technology loads at the transmission level, and approximately a further 300 MVA contracted at the 110 kV distribution level
Scope and limits: Contracted connection capacity (MVA), combining data centres with other 'new technology loads'; it is not metered consumption, not capacity in operation, and not utilization. Data frozen 30 June 2025, before CRU/2025236. Release date is from EirGrid's news release (26 Feb 2026); the PDF's metadata shows a later modification (20 Mar 2026). It is not a measure of utilization, and not a count of delayed projects.
Retrieved Oct 21, 2026.
Ofgem (Consultation: Curate - Demand Connections Reform, July 2026) · Jul 29, 2026
Between November 2024 and June 2025, contracted demand in the connection queue increased from 41 GW to 125 GW. Of this, around 73 GW are data centres. For a sense of scale, peak demand in Great Britain in 2025 was 45 GW.
Scope and limits: Contracted connection offers in a queue, not capacity under construction, not consumption, and not utilization; Ofgem itself says many projects may be speculative and is proposing a commitment fee (GBP 237,500-712,500 per MW) and milestones. Ofgem's own press release the same day says data centres account for 'at least 80GWs', inconsistent with the consultation's ~73 GW. It is not a measure of utilization, and not a count of delayed projects.
Retrieved Oct 21, 2026.
National Energy System Operator, GB (Demand Call for Input High Level Summary, March 2026) · Mar 11, 2026
The NESO Demand CFI received 243* responses representing over 90GW of demand capability. […] Only 32% of data centre projects have secured off-takers, while 68% have not yet secured one, often pending a firm grid connection date or with negotiations under way.
Scope and limits: Voluntary developer survey of transmission-queue projects; NESO states the insights are 'indicative only' and 'represent developer intent, not confirmed deliverability'. Not connected capacity, consumption, or utilization. The document states only 'March 2026'; the date used is the PDF creation date (11 Mar 2026). It is not a measure of utilization, and not a count of delayed projects.
Retrieved Oct 21, 2026.
OCCTO, Japan (全国及び供給区域ごとの需要想定 2026年度 / National and area demand forecast FY2026) · Jan 21, 2026
最大需要電力(合計)は、2026 年度で+83 万 kW、2030 年度で+420 万 kW、2035 年 度で+762 万 kW を個別計上する結果となった。 また、需要電力量(合計)は、2026 年度で+67 億 kWh、2030 年度で+308 億 kWh、 2035 年度で+568 億 kWh を個別計上する結果となった。
Scope and limits: A forecast of grid demand built from connection applications (projects judged high-probability, e.g. those at the construction-cost-contribution contract stage), combining data centres and semiconductor factories; not metered consumption, not capacity in operation, and not utilization. Japanese text. Finquill's translation: "Peak demand (total) is individually counted at +830 MW in FY2026, +4,200 MW in FY2030 and +7,620 MW in FY2035; energy demand (total) at +6.7 TWh, +30.8 TWh and +56.8 TWh" (converted from 10,000 kW and 100 million kWh units). It is not a measure of utilization, and not a count of delayed projects.
Retrieved Oct 21, 2026.
OCCTO, Japan (全国及び供給区域ごとの需要想定 2026年度 / National and area demand forecast FY2026) · Jan 21, 2026
なお、前回想定と比較すると、主にデータセンターにおいて、事業者の工事延期・遅延 や設計変更等に伴う計画変更により、運開時期や最終需要規模に到達する時期が後ろ倒 しとなることから、需要電力量(使用端合計)の伸びも後年度へ後ろ倒しになっており […] 2033 年度までは前回 想定を下回る推移となっている。
Scope and limits: Describes a revision between two forecasts, attributed by OCCTO to operators' plan changes; it is not a count or list of delayed projects, not consumption, and not utilization. Japanese text. Finquill's translation: "Compared with the previous forecast, mainly for data centres, plan changes due to operators' construction postponements, delays and design changes push back the start of operation and the time to reach final demand, so growth in energy demand also shifts to later years [...] it runs below the previous forecast through FY2033."
Retrieved Oct 21, 2026.
Fingrid Oyj, Finnish TSO (News release, 18 Aug 2026) · Aug 18, 2026
By mid-August, the planned final combined capacity of data centre projects that have signed connection agreements totalled nearly 5 gigawatts based on information provided by project developers, including projects connected to distribution networks.
Scope and limits: Planned final capacity under signed connection agreements, as reported by developers; Fingrid states signing does not guarantee full build-out and projects do not immediately use their full declared capacity. Not consumption, not capacity in operation, not utilization. It is not a measure of utilization, and not a count of delayed projects.
Retrieved Oct 21, 2026.
Singapore Economic Development Board and IMDA (Fact sheet: DC-CFA2 proposals selected, 21 Aug 2026) · Aug 21, 2026
EDB and IMDA provisionally allocated 50MW of DC capacity to each of the following companies (listed alphabetically): a) Digital Realty b) Equinix c) Keppel Data Centres d) ST Telemedia Global Data Centres […] DCs supported under DC-CFA2 will locate their facilities on Jurong Island.
Scope and limits: A provisional capacity allocation (permission to build), not capacity built, energised or in use, and not utilization; operators' build timelines are not stated. It is not a measure of utilization, and not a count of delayed projects.
Retrieved Oct 21, 2026.
Singapore Ministry of Energy, Trade and Industry (written parliamentary reply on DC-CFA2, 10 Sep 2026) · Sep 10, 2026
The data centres which have been provisionally awarded capacity under the second Data Centre Call for Application (DC-CFA2) exercise will have a combined capacity of 200 megawatts (MW). This will represent around 12 per cent of Singapore’s total data centre capacity.
Scope and limits: Capacity figures (MW of data-centre capacity), not electricity consumption and not utilization; the 12% denominator is not defined in the reply. The awards are provisional. It is not a measure of utilization, and not a count of delayed projects.
Retrieved Oct 21, 2026.
European Commission (COM(2026) 501, Strategic Roadmap for Digitalisation and AI in the Energy Sector; Council register copy ST 10101/26) · Jun 3, 2026
The EU aims to triple its data centre capacity within 5-7 years […] Data centres currently account for around 2.5% of EU electricity consumption […] their installed capacity is expected to grow from approximately 12 GW in 2025 to around 28 GW by 2030
Scope and limits: Installed-capacity estimate and forecast from a Commission-contracted study, not measured EU-wide consumption and not utilization. Commission documents disagree on the consumption share: the Sept 2026 rating-scheme delegated act (C(2026) 3472) cites 68 TWh in 2024 (IEA) and elsewhere 'around 1.5-2.0%'. It is not a measure of utilization, and not a count of delayed projects.
Retrieved Oct 21, 2026.
Coverage scope: Global. When planned AI capacity becomes operational, and what holds it up. Operator milestones: CoreWeave's active and contracted power, lease delivery windows and its one documented delay; Oracle and Nebius capacity statements; Microsoft's capacity remarks. Equipment and components: NVIDIA, ASML and SK hynix. Grid access by region: PJM and ERCOT in the US; Ireland, Great Britain, Japan, Finland, Singapore and the EU. Regional findings stay in their region. Connection requests, forecasts and allocations are not connected load, and nothing here is a utilization measure. Out of scope: financing (see "Financing the AI buildout"), profitability, and chip export controls.
Update history
- Update 1 · Oct 27, 2026 · this page